Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Linsil (6/04)
See Bpp Exam it the number of Linsil (6/04), see it’s answers of part a, the direct labour hours why it has made 1.25 multiply by 100/90???
It should have simply made 90% of 1.25. In the question the note number 3 it said that 10% decrease in labour, so labour hours should have reduced, but the answer in the book has showed an increase????
PLEASE REPLY Thanks in advance
Sorry – I do not have access to the BPP exams.
It is found in BPP exam kits number 52 (new edition), in the january 2010 edition it is found in number 45.?????
PLEASE REPLY
Note 3 says that the standard used had expected that there would be a 10% decrease in labour hours.
However, this did not happen – they did not buy a new machine.
So the standard labour hours should in fact have been higher (100 hours for every 90 hours that they had been expecting).