Hi everyone, can anyone tell me if there’s question which says, that is ”lifecycle costing used for planning”? i always mark true because i have read somewhere that ‘lifecycle costing’ can be used for forward planning. but it is always false.
can anyone confirm about this please.
Lifecycle costing is used to either decide whether or not a new product is worth producing, or to help determine a selling price for a new product.
I do explain this in my free lectures.