• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

learning rate

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › learning rate

  • This topic has 9 replies, 4 voices, and was last updated 10 years ago by John Moffat.
Viewing 10 posts - 1 through 10 (of 10 total)
  • Author
    Posts
  • April 14, 2015 at 6:43 pm #241305
    Ursula
    Member
    • Topics: 2
    • Replies: 1
    • ☆

    Please kindly help me solve the section A question 11.A company is intending to sell a new product. I do not understand how the 87.5% was arrived at as the answer. i got 75%

    April 15, 2015 at 7:35 am #241345
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You will have to tell me which exam you are referring to!

    April 16, 2015 at 10:22 am #241510
    Ursula
    Member
    • Topics: 2
    • Replies: 1
    • ☆

    Please I’m referring to the new ACCA F5 Mock Exams(Objective test exams). Question 11

    April 16, 2015 at 12:48 pm #241519
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    I assume that you are meaning our mock exam (and not the ACCA specimen exam).

    As it states on the page before the exam, questions are selected at random from a bank of questions and so you will not get the same questions, in the same order, each time you attempt it. So ‘question 11’ means nothing to me.
    In future, as it says before the test, you must copy the question here if you have a problem.

    However, I think I have found the one that you are referring to.

    The average time per unit if they make 2 units is (8+6)/2 = 7 hours.
    So the learning rate is 7/8 = 87.5%

    (The doubling rule applies to the average time per unit)

    The free lecture on learning curves may help you.

    April 22, 2015 at 5:57 pm #242214
    N
    Participant
    • Topics: 4
    • Replies: 2
    • ☆

    ok..i got 87.5% too using the formula: y=ax^b, although im not sure if its the right way to do it, plus its also time consuming:
    the values which i used were as follows:

    y= 7 (av. cumulative time)
    a=8 (since this is the time req for the 1st one)
    x=2 (for # of units)
    calculations to get b:
    y=a(x^b)
    7=8(2^b)
    7/8=2^b
    b=log(7/8) / log2
    b=-.19264…
    since b=logLR/log2, therefore -.19264*log2=logLR
    logLR=-0.0579….
    so LR = 10^-0.0579 = 0.875
    CORRECT?

    April 22, 2015 at 8:23 pm #242229
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    Well, yes it is obviously correct – I wrote in my previous reply that the answer is 87.5%

    However, much easier is to use the doubling rule as I did in my previous reply (and you can be tested specifically on the doubling rule rather than on using the formula).

    April 28, 2015 at 5:13 pm #243109
    danique
    Member
    • Topics: 3
    • Replies: 4
    • ☆

    Hi could I have some assistance with a question I’m getting two answers and they are both among the multiple choice answers. Here goes the question

    The times taken to produce each unit of the first four batches of a new product were as follows:
    Batch # time taken
    1. 100 mins
    2. 70 mins
    3. 59 mins
    4. 55 mins

    What was the rate of learning closest to?

    I’m getting 85% when I use the cumulative time taken at batch 2 which is 170 and divide it by 2

    However when I use the cumulative time taken for batch 4 I’m getting 84.3%. At batch 4 the cumulative time taken is 284…..284/4=71
    71/100=r(squared) etc

    Need to knw which would work in this scenario……

    April 29, 2015 at 7:19 am #243187
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    I am surprised if the question has both answers in the choices.

    However, if it does then 84.3% is the better choice. The reason is that you would not expect the learning rule to work precisely in practice, and the more results you looked at the better.

    April 29, 2015 at 3:03 pm #243243
    danique
    Member
    • Topics: 3
    • Replies: 4
    • ☆

    ok thanks

    April 29, 2015 at 4:06 pm #243251
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 10 posts - 1 through 10 (of 10 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on MA Chapter 4 Questions Cost Classification and Behaviour
  • maryrena77 on The nature and structure of organisations – ACCA Paper BT
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour
  • John Moffat on The financial management environment – ACCA Financial Management (FM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in