Hey All,
Just wondering if anyone can help with this question, I am currently doing questions from the BPP P&R KIT I’m looking at question 40.8.
For those whom don’t have access to this p&r kit, the question goes like..
A company has estimated that an 85% learning curve rate will apply to the production of a new item for which the time to produce the first unit was 800 hrs.
What is the expected time to produce the 9th unit.A. 370.86 hrs
B. 417.61 hrs
C. 477.92 hrs
D. 491.30 hrsI got as far as.. log (0.85)÷log (2)= -0.2344652
Then I got confused, looking back at the answer doesn’t help as I feel the way the answers are written doesn’t necessarily correlate to how I’ve been taught.
I was thinking 800hrs X 9 units (-0.2344652)
Please help!
November 12, 2014 at 12:30 am #209224Hi
Not seen the text book.. However the answe is a :371
Total time for 9 units :800×9 ^ -0.2344652 x 9 =4301
Total time for 8 units : 800×8 ^-0.2344552 x 8 =3930
4301 – 3930 = 371.
Hope this helps
Thanks
November 12, 2014 at 12:53 am #209225Thank you I manged to work it out in the end 😉
Yep I got the same answer
Happy studying;)November 12, 2014 at 2:07 pm #209363Please read technical article on acca website where this learning curve is well explained.
November 12, 2014 at 5:28 pm #209421Or better than that would be to watch the free lecture on here!