BB plc has received an order to make eight units of a new product called the Betty Boop. The time to produce the first unit is estimated to be 100 hours, and a 80% learning curve is expected. The rate of pay is $6 for each hour. The direct materials for each unit is $2,500 and the fixed costs associated with the order are $9,600.
What is the average cost of each unit (to the nearest $) for this order of product Betty Boop? A $4,007 B $4,180 C $6,158 D $10,160
I know it looks like an easy question but I seem to get the wrong answer I dont know why Please help