Should idle time be considered when calculating labour efficiency variance?
John MoffatJohn MoffatTutor5y ago#1
Yes, in the sense that the standard hours are the standard hours worked (after idle time). If we are told the standard rate of pay then we need to calculate the standard cost per working hour to use for the calculation of the efficiency variances. I explain how in my free lectures on idle time variances.