Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Labour efficiency variance with idle time
- This topic has 1 reply, 2 voices, and was last updated 8 years ago by John Moffat.
- AuthorPosts
- December 8, 2015 at 9:45 am #288933
Hi John
I understand that with idle time we work out the hourly rate by multiplying the standard rate per hour by the percentage of time actually worked. Say $10*0.95 (assumes a stn idle time of 5%). So the idle time variance I get.
But where does this fit into the overall efficiency variance.
Do we take hours actually worked vs budgeted hours per unit (flexed to production levels) and multiply by:
a) the standard rate per hour?
or
b) the working rate per hour (adjusted for idle time)?And likewise, if this was a rate variance question with idle time thrown in, how would we go about solving it?
I am trying to get my head around it logically so I can understand what I am doing.
Thank you very much for your help.
December 8, 2015 at 11:14 am #288956The free lecture on advanced idle time variances does go through all of this!!
For the efficiency variance you always compare the actual hours worked with the standard hours for the actual production, and cost out at the standard rate per working hour (which would not be $10 x 0.95 if $10 was the pay rate, it would be $10 / 0.95)
The labour rate variance is always calculated in the normal way. i.e. the actual hours paid, at the difference between the actual pay rate and the standard pay rate.
- AuthorPosts
- You must be logged in to reply to this topic.