A company had 80 direct production workers at the beginning of last year and 60 direct production workers at the end of last year. During the year a total of 45 employees had left the company. The labour turnover rate for last year was: A 21.4% B 35.7% C 64.3% D 75.0% sir, i did not understand how u got option B as answer ? 2.budgeted production in factory for next period is 4800 units. each unit requires five labour hours to make. labour is paid 10 per hour. Idle time represents 20% of the total labour time. what is the budgeted total labour cost for the next period? can u plz answer this with full process
Aarchana11y ago#1
Budgeted and actual production data for the year that has just ended are as follows. Product Budgeted production Actual production Units Standard machine hours Units W 15,000 3,000 12,000 X 20,000 8,000 25,000 Y 14,000 7,000 16,000 Z 6,000 9,000 5,000 Total machine hours worked in the period amounted to 29,000 hours. sir, i this question we are given list of standard hours.. but why these hours used as budgeted and we have to calculate standard hours??
John MoffatJohn MoffatTutor11y ago#2
Question 1: There is not enough information in the question (we need to be told how many workers there were at the end of the year)
John MoffatJohn MoffatTutor11y ago#3
Question 2: Hours needed for production = 5 x 4800 = 24000 SInce 20% of hours paid are idle, it means paying for 24,000 x 100/80 = 30,000 hours Cost if $10 per hour, so total of $300,000
John MoffatJohn MoffatTutor11y ago#4
Question 3 Standard hours are budgeted hours per unit.