Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › June 2018 Ruva
- This topic has 3 replies, 2 voices, and was last updated 6 years ago by
John Moffat.
- AuthorPosts
- November 29, 2018 at 11:20 am #486401
Anonymous
Inactive- Topics: 1
- Replies: 1
- ☆
Hi Sir John Moffat,
1) what is the discount rate for phase 1 and phase 2? I use all equity cost of equity engaged same as project E at 12% and apply in MM prop 2 (tax) and obtain new WACC. And I got 11%.
2) Is the scenario in Ruva project E an option to expand rather than option to delay? For construction industry, normally it would’ve been option to abandon.
3) investment 320m in year 4 for phase 2 would be discounted at 5% kd as per question.
I got negative NPV with cost of debt but positive NPV if discounted at WACC 11%.If cost of debt is more reasonable, what is the reason for this? Do I make assumption that the reason is cos investment 320m is entirely financed out from debt financing with outlook that soft capital rationing limits the investment? Also optimum capital structure at best with increase of debt and obtain the tax benefit.
Therefore reject Project E on director’s proposal .
4) how real options build on NPV when evaluating investment decision?
It considers uncertainty in the future and add/reduce the value to have the option to expand/delay over time and volatility of project as compared to without the option. Hence BSOP model is used on phase 2 and traditional NPV on phase 1. Extra investment undertaken if PV> investment.November 29, 2018 at 2:53 pm #486423Please check you are referring to the correct exam – there is no question called Ruva in the March/June hybrid questions.
November 30, 2018 at 11:08 am #486561Anonymous
Inactive- Topics: 1
- Replies: 1
- ☆
Here is the scenario :
Project E is two phase project.
Phase 1 initial outflow immediately and cash inflows earned.
Phase 2 investment $320m at start of year 5. Annual inflation adjusted after tax cash inflows $50m. Phase 2 will be sold at end of 10 year life for $50m. Uncertainty for these cash flows and volatility standard deviation given.Ruva MV debt to equity ratio 40:60.
Cost of debt 5%. Risk free rate 3%.Project E is not normal business of Ruva and all equity of co industry similar to Project E is 12%.
Ruva CEO believes that phase 2 investment $320m should be discounted at cost of debt, better estimate of its opportunity cost.
——
I managed to figure out for q4. In addition to above questions,
How to estimate the value of project E
if not delay decision?My answer:
(i)PV cf in
pHase 1 discounted at wacc using MM proposition
+ phase 2 investment 320m at kd
+ Phase 2 cash inflows include sale of project E at Kd ( instead of WACC like in phase 1)November 30, 2018 at 3:47 pm #486588Sorry, but again – this is not a published ACCA question (and you surely have an answer you check to?)
- AuthorPosts
- The topic ‘June 2018 Ruva’ is closed to new replies.