Apologies guys – 1 more question from me;
How is the EV figure of $101,700 calculated – I get the PBIT figures for the 3 scenarios – just don’t know how the Expected PBIT figure is found.
Thank you!
Hi
Can you please explain to me how to work out the PBIT for the 3 scenarios as I am so stuck and confused; if you can help, it would be much appreciated.
In regards to how the figure $101,700 is calculated. You add up all the three PBIT and divide by 3.
Can you please help me on how to work out the PBIT for the 3 scenarios.
Many thanks in advance,
Raja