I checked F5 June14 answers (question 1 part a) against examiner’s report (in ACCA website), the report says the OAR should have been calculated using Machine hours, but in the answer it is calculated using labour hours. it is confusing, any Idea about this ?
The examiners report has a typing mistake.
It should have been labour hours – the question specifically says to use labour hours.
Thanks for clarifying 🙂