Job costingForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Job costingThis topic has 3 replies, 2 voices, and was last updated 3 years ago by John Moffat.Viewing 4 posts - 1 through 4 (of 4 total) AuthorPosts December 13, 2020 at 6:48 pm #599844 GMukhMemberTopics: 1Replies: 1☆BPP exam kit – 9a.5:Why the value of CWIP at the end of the period for job BB15 is not included in the calculation?“Job number BB15 was completed on the last day of the period” – what is the effect of this statement in the calculation?Thank you. December 14, 2020 at 7:55 am #599876 John MoffatKeymasterTopics: 56Replies: 53850☆☆☆☆☆If it was completed then there was no work-in-progress at the end of the period. WIP is when something is not completed. December 14, 2020 at 8:23 am #599880 GMukhMemberTopics: 1Replies: 1☆Ok. Thank you so much. December 14, 2020 at 1:04 pm #599900 John MoffatKeymasterTopics: 56Replies: 53850☆☆☆☆☆You are welcome 🙂AuthorPostsViewing 4 posts - 1 through 4 (of 4 total)The topic ‘Job costing’ is closed to new replies.