sir this is silly doubt, just a small confusion
i have wriiten in my short notes tht irr is maximum return v can expect from the project.
os it coorect sir??
No it is not correct. The IRR is the rate of interest at which the NPV is zero.
The return from the project might be higher or lower than the IRR.