• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

IRR

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › IRR

  • This topic has 7 replies, 3 voices, and was last updated 4 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • October 17, 2014 at 12:47 pm #204715
    amisalut
    Member
    • Topics: 9
    • Replies: 9
    • ☆

    Dear tutor,

    in bpp revision kit answer to q18 “Slow Fashions Co” (6/09) part (a) it is said that IRR cannot be calculated on proportions of project. Why?

    And in part b) we are asked to calculate max % rate that the co is ready to pay to finance investment in all the remaining projects. In answer it is said that IRR is irrelevant, because it results in NPV=O. Ok, I understand. Then it is said that the maximum cost of capital acceptable to the additional finance required is basic cost of cap+profitability index of projects rejected which equals 17.652%. I tried to discount cash flows of rejected projects at 17.652%, but it gave me negative NPV. So I can’t understand the meaning of this figure…

    October 17, 2014 at 5:44 pm #204754
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54665
    • ☆☆☆☆☆

    BPP’s answer is very poor.

    In part (a)) I think they have been copying the examiners answer but missed part of what he wrote!!!!!!!

    You certainly can calculate the IRR on proportions of projects, but there is no point because the IRR of (say) 50% of a projects flows will be the same as the IRR on the whole project flows, and we know what the IRR’s are.
    What they should have said (and what the examiner effectively said) is the we can’t take a weighted average of the individual flows – that won’t work.
    So we have to calculate the IRR of the whole ‘package’.

    With regard to part (b) what you are forgetting is that we are after the maximum rate worth paying for short-term finance. We only need the funding for one year (because in one year we can get more funding at our current cost of capital). So for that one year we are prepared to pay 17.652%. We certainly would not be prepared to pay that if it were long-term funding because (as you say) we would have a negative NPV.

    October 18, 2014 at 2:00 pm #204845
    amisalut
    Member
    • Topics: 9
    • Replies: 9
    • ☆

    Thank you very much!!!

    October 18, 2014 at 7:48 pm #204877
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54665
    • ☆☆☆☆☆

    You are welcome 🙂

    July 18, 2020 at 2:44 am #577251
    student0001
    Member
    • Topics: 13
    • Replies: 24
    • ☆

    Dear Sir

    If we can calculate IRR for a portion of the project, then is IRR of choice 1 calculated this way?

    Project Initial investment 2010 2011 2012 2013 2014 2015
    PO805 -120 25 55 75 21
    PO801 -620 280 400 120
    PO802 (whole) -640 80 120 200 210 420 -30
    PO802 (71.875%) -460 58 86 144 151 302 -22
    Total -1,200 363 541 339 172 302 -22
    IRR 14.5%

    thanks

    July 18, 2020 at 9:58 am #577276
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54665
    • ☆☆☆☆☆

    Yes – that is correct.

    July 18, 2020 at 2:17 pm #577298
    student0001
    Member
    • Topics: 13
    • Replies: 24
    • ☆

    Thank you Sir.

    July 18, 2020 at 2:27 pm #577301
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54665
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • The topic ‘IRR’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • MikeLittle on Civil Law, Common Law, Criminal Law – ACCA Corporate and Business Law (LW) (ENG)
  • beata443c on Civil Law, Common Law, Criminal Law – ACCA Corporate and Business Law (LW) (ENG)
  • heary123@ on Group SFP – Unrealised profit and inventory in transit – ACCA Financial Reporting (FR)
  • heary123@ on Group SFP – Unrealised profit and inventory in transit – ACCA Financial Reporting (FR)
  • John Moffat on PM Chapter 15 Questions Financial Performance Measurement

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in