- This topic has 3 replies, 2 voices, and was last updated 10 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- You must be logged in to reply to this topic.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Investment appraisal – technical article
sir,
do we have to add the option to delay ( call option value) and NPV value to find the total project value?
No.
The previous examiner did so in his answer (and for that reason most revision kits, and I am afraid my lecture also, do add the value of the option).
However, he was wrong and that is the reason for the article.
Using the formula gives the total value of the project including the option.
(The value of the option itself is the different between what you get from the formula and what the NPV is ignoring the option)
Thankyou Sir ?
You are welcome 🙂
