• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

December 2025 ACCA Exams

Post comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

Investment Appraisal

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › Investment Appraisal

  • This topic has 7 replies, 2 voices, and was last updated 10 years ago by John Moffat.
Viewing 8 posts - 1 through 8 (of 8 total)
  • Author
    Posts
  • April 28, 2015 at 11:15 am #243056
    sam
    Member
    • Topics: 2
    • Replies: 4
    • ☆

    Good Afternoon
    Dear Sir,
    Please provide me the answers of the following:

    What is the main difference b/w ARR And IRR?

    What is the meaning of IRR is the rate of return at which NPV = 0 ?

    In Capital Rationing when ranking the projects from highest P1 to lowest P1 why do we rank the project as first (higest) when it has ZERO NPV ?
    this question was tested in JUNE 2014 Q:1 part (b)

    Regards
    Samran Saqib
    ACCA Student

    April 28, 2015 at 12:05 pm #243076
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54801
    • ☆☆☆☆☆

    As far as the first two questions are concerned, you must watch the free Paper F9 lectures – I cannot type out the whole lecture here!!!!

    ARR is an accounting measure (accounting profits and SOFP values); IRR is dealing only with cash flows and is the rate of interest at which the NPV is zero.

    The main use of the IRR is the fact that in practice it is impossible to be certain of the cost of capital. However, if we feel that the cost of capital is likely to be less than the IRR then the project will be acceptable, if not then it won’t be. It gives us an idea of the sensitivity.

    In respect of your third question, the examiner states the reason in his answer!! Project E (with zero NPV) has to be undertaken – it says so in the question (immediately below the heading “Project E”). Were it not for this then it certainly would not be ranked first.

    April 29, 2015 at 11:08 am #243223
    sam
    Member
    • Topics: 2
    • Replies: 4
    • ☆

    Many Thanks Mr.John 🙂

    April 29, 2015 at 3:51 pm #243248
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54801
    • ☆☆☆☆☆

    You are welcome 🙂

    May 1, 2015 at 4:31 pm #243531
    sam
    Member
    • Topics: 2
    • Replies: 4
    • ☆

    i have 1more question in Past ppr june 2013 q:1 regarding working capital cash flows it says in the q:
    Initial invstmnt in Wc is $500,000.
    Investmnt in Wc will be subject to general rate of inflation which is expected to be 4.7% per year.

    Wc requirement ($000)

    In T0 ($500)
    T1 $ (523.5)
    T2 $ (548.1)
    T3 $ (574)

    Wc c.flows ($000)
    In T0 ($500)
    T1 $ (24)
    T2 $ (25)
    T3 $ (26)
    T4 $ (27) why? ?
    In T4 it Wc is recoverd fully usually why its not 574 positive in T4 ? ?

    May 1, 2015 at 6:55 pm #243570
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54801
    • ☆☆☆☆☆

    In future, please start a new thread when you are asking about a different question. We cannot give private tuition free of charge and so our answers to question are trying to help everybody.

    This answer was very unusual. Usually we assume that all of the working capital is recovered at the end of the project. The reason it did not happen here is that the question says that the machine will be replaced. Therefore presumably we will still continue to produce the product, and therefore presumably the working capital will still be needed.

    It was unfair of the examiner, and he realised that. He said that if the working capital had been recovered, then it would still get full marks (even though, obviously, the final answer would be different.)

    May 3, 2015 at 7:57 am #243740
    sam
    Member
    • Topics: 2
    • Replies: 4
    • ☆

    Appreciated Sir I got that it would not happen next time 😮

    now regarding the above question it means we donot have to worry about what examiner did and we just have recover the working caplital after the end of the project?

    May 3, 2015 at 10:12 am #243755
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54801
    • ☆☆☆☆☆

    Always assume that working capital is recovered at the end of the project, unless the question specifically says that it is not recovered.

  • Author
    Posts
Viewing 8 posts - 1 through 8 (of 8 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on Financial management objectives – ACCA Financial Management (FM)
  • John Moffat on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • RAJD on Financial management objectives – ACCA Financial Management (FM)
  • rahmat786 on Activity Based Costing part 1 – ACCA Performance Management (PM)
  • John Moffat on PM Chapter 1 Questions Activity based costing

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in