Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › investment appraisal
- This topic has 9 replies, 3 voices, and was last updated 10 years ago by John Moffat.
- AuthorPosts
- December 3, 2014 at 10:24 am #216730
initial invest 24000 at time 0 generate inflow 5000 per 8 year 1st inflow occuring in 1 year time
what is the % IRR
plz sole ?December 3, 2014 at 11:04 am #2167535,000 x annuity df for 8 years = 24,000
So 8 year annuity d.f. = 24,000 / 5,000 = 4.800
If you look in the annuity tables along the 8 year row, then the rate of interest that gives 4.800 is 13%
December 3, 2014 at 12:46 pm #216802hello sir
a company has 3 projects with the following initial cost and npv
Project A : initial cost 20000 ; NPV 2000
Project B ; intial cost 30000 ; NPV 2400
Project C ; initial cost 10000; NPV 1200
capital available for lim,ited 40000
if project are divisible what is the maximum NPV can be acheved ?December 3, 2014 at 1:03 pm #216809AnonymousInactive- Topics: 0
- Replies: 33
- ☆
I think the answer is 4000?
100% project C, same with Project A which means only 10,000 left for project B so only 800 profit thereDecember 3, 2014 at 2:38 pm #216838a payment has agreed to lease for 8 yr with an equal annual payment payable at start of each yr
npV of agreement 52000 cost of capital 10%
what is a annual lease payment ?December 3, 2014 at 3:05 pm #216857thanx sir
December 3, 2014 at 3:33 pm #216877machine cost 7200
runing cost as follows
y1 7200
y2 9600
y312000
estimated scrap value as follows
y1 24000
y2 16600
y3 9600
cost of capital is 10%
what is annual equlent cost if replace machine every 2 yr /December 3, 2014 at 4:04 pm #216909Aleksandrs is correct with regard to the capital rationing problem.
December 3, 2014 at 4:05 pm #216910For the lease problem:
Suppose the lease payment is X per year.
The first payment is immediate (it is paid at the start of the year), so the PV is X.
There are then 7 payments. The PV of these is 4.868X (4.868 is the 7 year annuity factor).
So the total PV is X + 4.868X = 5.868XThis must be equal to 52,000
So X = 52,000 / 5.868 = $8862
December 3, 2014 at 4:09 pm #216913For the replacement problem:
The PV of the first machine is 7,963
So the EAC = 7963 / 1.736 = $4,587
- AuthorPosts
- You must be logged in to reply to this topic.