• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Interest rates

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › Interest rates

  • This topic has 8 replies, 2 voices, and was last updated 1 year ago by Simone.
Viewing 9 posts - 1 through 9 (of 9 total)
  • Author
    Posts
  • February 21, 2024 at 8:22 am #700777
    Simone
    Participant
    • Topics: 12
    • Replies: 33
    • ☆

    Hi,

    I wondered whether you could help with the following question:

    Benden Co is a manufacturer of premium priced clothing, based in Country B. Benden Co’s current share price is $2.00, having increased by $0.20 over the past year. Its latest dividend per share is $0.10, which is an increase of $0.02 compared to the previous year.

    Benden Co places monthly orders with a supplier for 10,000 buttons that are used in its manufacturing processes. Monthly demand is also 10,000 buttons.

    The cost per button is $0.08. The cost of ordering is $200 per order, and the cost of holding buttons in inventory is $1.00 per unit per year.

    The current terms are payment in full within 90 days, which Benden Co meets. The supplier has offered a discount of 3% for payment in full within 30 days.

    Assume a 360 day year.

    (4) Which is the annual percentage cost of ignoring the discount and continuing to pay after 90 days?

    Thanks
    Simone

    February 21, 2024 at 9:21 am #700778
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    I think it’s….
    First, you calculate the cost of holding demand is 10,000 buttons at $1.00 per unit per year, is $10,000.

    So, the number of orders placed per year would be 12 orders at * $200 = $2,400.

    The total cost of ignoring the discount can be calculated by adding the annual holding cost and the annual ordering cost. Therefore, the total cost of ignoring the discount would be $10,000 + $2,400 = $12,400.

    No calculate the annual percentage cost of ignoring the discount at 3% ( discount offered by the supplier ) is 3%, which is 3% * $12,400 = $372.

    To calculate the annual percentage cost, we divide the cost of ignoring the discount by the total cost of ignoring the discount and multiply by 100. Therefore, the annual percentage cost of ignoring the discount and continuing to pay after 90 days would be ($372 / $12,400) * 100 = 3%.

    February 22, 2024 at 10:45 am #700873
    Simone
    Participant
    • Topics: 12
    • Replies: 33
    • ☆

    Apparently it’s 18.54%, and they have used 3.09% to get to answer (see below), but I have no idea where 3.09% comes from…

    This can be converted into an annual equivalent by multiplying 3.09% by 360 days / 60 days to give 18.54%.

    Notes on incorrect answers

    18.00% – incorrectly based on the cost of the lost discount as a % of the amount paid after 90 days (288/9,600)
    3.09% is not annualised
    3% again is not annualised or based on the amount that would be paid after 30 days

    February 22, 2024 at 11:23 am #700877
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    Where is this question from?
    I can’t help you if I don’t know the question
    I am trying my best to work it out, so

    The 3.09

    Is (1+ 3/97) ^ 360/60

    3 Disc
    97 is 100 – disc
    360 days a yr
    reduced by 60

    Or annual equivalent
    3.09 * 360/60 = 18.54%

    February 22, 2024 at 3:02 pm #700889
    Simone
    Participant
    • Topics: 12
    • Replies: 33
    • ☆

    The question is in the original post…

    “The current terms are payment in full within 90 days, which Benden Co meets. The supplier has offered a discount of 3% for payment in full within 30 days.

    Assume a 360 day year.

    (4) Which is the annual percentage cost of ignoring the discount and continuing to pay after 90 days?”

    February 22, 2024 at 3:44 pm #700893
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    No, I am asking you where this question is from.

    Which exam kit?

    I can’t find it in BPP or Kaplan

    February 24, 2024 at 7:43 am #700999
    Simone
    Participant
    • Topics: 12
    • Replies: 33
    • ☆

    Apologies.
    I’m trialing BPP’s Stay Sharp subscription – The question is in Step Ladder 2.

    February 24, 2024 at 11:21 am #701012
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    I don’t have access to this question anyway :0-)

    Are you happy with my answer:

    The 3.09

    Is (1+ 3/97) ^ 360/60

    3 Disc
    97 is 100 – disc
    360 days a yr
    reduced by 60

    Or annual equivalent
    3.09 * 360/60 = 18.54%

    February 24, 2024 at 2:45 pm #701027
    Simone
    Participant
    • Topics: 12
    • Replies: 33
    • ☆

    Thank you so much for your help, but I’m afraid I don’t get it, and to be honest I am not going to spend anymore time on it – I’m going to move on. Your initial answer of 3% makes sense and that’s the answer I got.

    My frustration with BPP is that they throw in curveball questions and answers that haven’t be covered in the workbook and they provide no explanation in their answers. They just expect you to know how the answer was calculated. If we knew that, we’d all pass our exams first time without needing tuition.
    Which is why I am seriously considering not using them for my PM exams in June.

  • Author
    Posts
Viewing 9 posts - 1 through 9 (of 9 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ken Garrett on Project management – ACCA Strategic Business Leader (SBL)
  • Kim Smith on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Farhaan on Project management – ACCA Strategic Business Leader (SBL)
  • Ken Garrett on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • thienan0110 on Interest rate risk management (1) Part 5 – ACCA (AFM) lectures

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in