• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

IFRS 15

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBR Exams › IFRS 15

  • This topic has 3 replies, 2 voices, and was last updated 1 year ago by Stephen Widberg.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • March 19, 2024 at 6:51 pm #703172
    adarsh1997
    Participant
    • Topics: 646
    • Replies: 282
    • ☆☆☆☆

    Hello,

    Regarding contract modification, the modification is accounted for as a separate contract if :
    – The price increases by an amount that reflects the stand alone selling prices of the additional goods or services.

    Could you please explain what does this mean?

    Thanks

    March 20, 2024 at 8:24 am #703203
    Stephen Widberg
    Keymaster
    • Topics: 16
    • Replies: 3396
    • ☆☆☆☆☆

    Please re-read the section in our notes (Section 6 of revenue).

    If it still doesn’t make sense please come back to me.

    Example would be a contract to build a house – modification might be to landscape the garden.

    🙂

    March 21, 2024 at 7:17 pm #703275
    adarsh1997
    Participant
    • Topics: 646
    • Replies: 282
    • ☆☆☆☆

    Hello,

    I’ve read the notes however, I am still having some difficulties to understand the idea behind.
    Please help me on that.

    Thanks.

    March 22, 2024 at 8:43 am #703295
    Stephen Widberg
    Keymaster
    • Topics: 16
    • Replies: 3396
    • ☆☆☆☆☆

    Example

    Hotel prices:
    – Room 100
    – Breakfast 10
    – Room and breakfast 107

    Customer buys room only for 100
    If she later changes her mind and says she wants breakfast as well:

    If the hotel charges her 10 for breakfast – 2 separate contracts
    If the charge is only 7 – then 1 single contract (and the price would be pro-rated to the 2 performance obligations).

    All very academic 🙂

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • singhjyoti on Conceptual Framework – ACCA SBR lecture
  • John Moffat on Time Series Analysis – ACCA Management Accounting (MA)
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Govere on The use of ratios and comparisons in auditing

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in