Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › IAS11 – Construction contracts (Example 5) Open tuition materials
I am having a problem with example 5, I know it says when there is more than one period the amounts are cumulative, but I’m not getting generalize cost recognised can you please offer some explanation.
Thank you.
From memory, isn’t example 5 where there is a forecast loss over the whole contract? If so, general costs is the balancing figure necessary to result in recognizing in full the forecast loss in the year in which it is first forecast?