Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › IAS 11 CONSTRUCTION CONTRACT (COST PLUS CONTRACTS)
- This topic has 3 replies, 2 voices, and was last updated 11 years ago by MikeLittle.
- AuthorPosts
- February 21, 2013 at 11:40 am #118379
it says in COST PLUS CONTRACTS ,” the contract costs attributable to the contract, WHETHER OR NOT REIMBURSABLE, can be clearly identified and measured reliably….”
why REIMBURSABLE? like this a contract … so whose gonna reimburse..? how the contract works in this situation?can u give a practical example of COST PLUS CONTRACTS??
February 21, 2013 at 7:01 pm #118440I’m back again to asking you to contact the publisher!
A cost plus contract is one where the costs are added / accumulated as the contract progresses and are invoiced to the customer on a regular basis calculated as “Costs to date + agreed profits calculated based on those costs”
February 22, 2013 at 12:10 am #118467i know f7 paper doesnt ask examples..but if we know how something through some procedures…. it starts making sense and concept…
okay il contact publisher… 🙂February 22, 2013 at 7:54 am #118482Thanks again
- AuthorPosts