A cost centre is charged with the following actual overhead costs for a period:Allocated costs$28,720 Apportioned costs $10,260 Overheads were absorbed in the cost centre over the period on 1,760 actual labour hours at a predetermined absorption rate of $21·50 per hour. Actual labour hours worked in the period were 90 hours above budget.
What was the overhead over/under absorption in the cost centre?
A: $1,140
B: $1,935
C:$3,055
D: $9,1204
FIA Forums
I guess A is the correct one, please confirm asap.
Guess!
Total OH = 28720 + 10260 = 38980
Budgeted OHAR = 21.50
Overheads are absorbed over 1760 hrs, so 21.5 x 1760 go into production = 37840.
Under absorbed = 38980 - 37840 = 1140
Your lucky guess has paid off!
Sign into reply to this topic.
