Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBL Exams › Home deliver Dec 2011
Sir, in b, why are the faults of documentation included in post implementation review?
The documents were inappropriately distributed to agents as many of them didn’t receive. There is no way that this thing is related to the product (post implementation review). I thought this should be in post project review. Please make this clear to me.
I think the distinction between the two reviews can be blurred. Probably this could be in either.