Forums › ACCA Forums › ACCA MA Management Accounting Forums › Help needed with Absorption costing Question, please!
- This topic has 2 replies, 2 voices, and was last updated 12 years ago by ainemoyles.
- AuthorPosts
- March 27, 2012 at 12:26 am #51983
Can somebody please help me with the question below. Thanks!
A company manufactures two products L and M in a factory divided into two cost centres, X and Y. The following budgeted data are available:
Cost centre X Y
Allocated and apportioned fixed overhead costs
x- $88,000
y- $96,000Direct labour hours per unit
x y
:Product L 3·0 1·0
Product M 2·5 2·0
Budgeted output is 8,000 units of each product. Fixed overhead costs are absorbed on a direct labour hour basis.What is the budgeted fxed overhead cost per unit for Product M?
A $10 B $11 C $12 D $13March 27, 2012 at 5:41 am #95799Hey,
well, I don’t gurantee that the answer is correct, but here are my calculations.
Answer : D = $13
x y
L 3 1
M 2,5 2
—- —
5,5 3 total hours for each cost centre.Then you need to find how much overheads are allocated per each centre per hour. Use total hours that are shown above.
= total overheads per cost cetnre / total number of hours per cost centrex = 88 000 / 5,5 = 16 000
y = 96 000 / 3 = 32 000Then using that small table above find the number of hours for each product in each cost centre.
We only need product M , so use only it’s data.
2,5 h in cost centre X and 2 hours in cost centre y.
Now multiply number for hours in each centre per relevant amount of overheads per hour.M = 2,5 x 16 000 + 2 x 32 000 = 104 000
That is total amount of overheads allocated for all 8.000 units.You need the number of overheads per unit, thus devide the amount of overheads above by number of units : 104 000 / 8 000 = $13
hope it helps 🙂
March 27, 2012 at 6:03 am #95800Thank you for the detailed explanation. You are right, I had the answer but no explanation. I could not get my head around this!
- AuthorPosts
- You must be logged in to reply to this topic.