PPinky13y ago
How to solve this? A Co. produces two products P and Q - that are both worked on in two departments - 1 and 2. Each Unit of P spends 1 hr in dept. 1 and 2 hrs in dept. 2. Each Unit of Q spends 2 hrs in dept. 1 and 2 hrs in dept. 2. The total budgeted production is as follows: P 5,000 units Q 10,000 units The total budgeted overheads are as follows: Department 1 $ 50,000 Department 2 $ 90,000 What is the overhead cost per unit for Product P?
John MoffatJohn MoffatAdmin13y ago#1
You need to calculate the overhead cost per hour in each of the two departments (by dividing the total cost by total hours for each department). Then you can calculate the overhead cost for Product P by charging 1 hour at the cost per hour in dept 1 and also 2 hours at the cost per hour in dept 2.
PPinky13y ago#2
Thanks a lot John! Got it! :-) Ans is $8.00($8.33). Am I right?