Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › F5 June 2010 Q2b – Labour Efficiency Variance
Hi there,
Can anyone explain to me how they get the amount 57,600 hours as the standard hours amount on q2 (b) of the June 2010 exam?
Thanks a lot
Steve
They produced 19200 cricket bats, and the standard time is 3 hours a bat.
So the standard hours for the actual production are 19200 x 3 = 57600