Forums › ACCA Forums › ACCA PM Performance Management Forums › *** F5 December 2014 Exam was.. Instant Poll and comments ***
- This topic has 688 replies, 98 voices, and was last updated 9 years ago by ramphothu.
- AuthorPosts
- December 1, 2014 at 8:36 pm #215504AnonymousInactive
- Topics: 2
- Replies: 14
- ☆
@chris 2400hrs s the total time stylists are expected to work for the year i.e 8 hrs a day, 6 days a wk,50 wks a year. Why r u multiplying by 3?
December 1, 2014 at 8:36 pm #215505Either way on the 20 kilo it’s 1 mark out of 100 at most so still happy days. Loved this paper.
Suggest we wait for Mr Moffat to post his answers to TPAR ratio rather than wasting our unproductive time going too and fro!!December 1, 2014 at 8:37 pm #215506Because there are three stylists?
December 1, 2014 at 8:38 pm #215509If you had 1 machine available for 100 hours and this was bottleneck, surely 3 machines would mean total time available on bottleneck would be 300 hours?
December 1, 2014 at 8:41 pm #215513AnonymousInactive- Topics: 2
- Replies: 14
- ☆
Guess we would wait then cos it doesn’t seem logical that you multiply the time for ALL stylists by 3 though I agree with u on the mats bit
December 1, 2014 at 8:43 pm #215514From what I remember
50 required:All in stock, therefore all sunk costs, however 30 need replacing in 2 weeks time therefore 8.5 x 30
The 20 need replacing too however not for 4 weeks therefore 8.2 x 20
Relevant cost of 425, that’s what I did.
December 1, 2014 at 8:44 pm #215518I agree James.
December 1, 2014 at 8:46 pm #215521James – thanks for the support too!! Never mind the theory of ‘loads of people made it “x” so it must be right’!!!
December 1, 2014 at 8:49 pm #215524I agree coolchihc.
Let’s wait and see. Not an easy one either way. It’s the question i left until last. Very happy with the mcq’s though. Think a lot easier than bpp texts or Kaplan and less ambiguous too. Number ones were pretty simple without too many curveballs.December 1, 2014 at 8:51 pm #215525When does John usually put answers up….a week later?
December 1, 2014 at 8:54 pm #215527From memory it’s not long after the paper is available online from acca. Not sure how long that takes though?
December 1, 2014 at 8:54 pm #215528Chris, it seems you got it right on tpars, but you were wrong on getting d and b, because you should have looked at contribution analysis, but not bottleneck analysis
December 1, 2014 at 8:54 pm #215529Must admit the same!
Study with Kaplan and there way exam kit was a lot more difficult than the questions today’s.Not as bad as I thought!
Is there somebody who does the answers on here soon then?
December 1, 2014 at 8:56 pm #215530James, out of 500 units you use 480, 20 are not used
December 1, 2014 at 9:00 pm #215532All mats were in continued use and all need replacing. D & b we’re correct from contribution per labour hour – as most people are saying!lol!!!
December 1, 2014 at 9:02 pm #215533From memory contribution was $24 for d and $5.25 per labour hour. Again,
We’ll wait to see what mr m says to see who’s correct.December 1, 2014 at 9:03 pm #215534I clearly remember and still visualize the sentence which told that 20 are not useful. Secondly, i have calculated contribution many times just to check, and got totally different answers from yours. Also, majority here is for A and D as well
December 1, 2014 at 9:04 pm #215535The aim was to max profit, but not contribution
I answered D and ADecember 1, 2014 at 9:04 pm #215536Ps my answer was based on return per labour hour (being the bottleneck resource) on the mcq.
December 1, 2014 at 9:05 pm #215538Do you agree on feedforward control and that issue with strategic planning though?
December 1, 2014 at 9:05 pm #215539Fair play Natalia.
That one may have got past me…damn them. Look forward to answers being posted!!December 1, 2014 at 9:05 pm #215540I calculated profit for D and A and than for D and B, the first were higher
without any additional calculationsDecember 1, 2014 at 9:06 pm #215542Defo on feed forward. Some of those answers were crazy ‘double loop back something’!!!!
December 1, 2014 at 9:07 pm #215543Chris, there was mot a bottleneck resource. There was just a shortage. This constitutes the difference in calculations
December 1, 2014 at 9:08 pm #215544Hahaha many peoplevwere caughtb;)
- AuthorPosts
- The topic ‘*** F5 December 2014 Exam was.. Instant Poll and comments ***’ is closed to new replies.