• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

F4 Anticipatory breach Case Explain plzzz!!!!!!!

Forums › ACCA Forums › ACCA LW Corporate and Business Law Forums › F4 Anticipatory breach Case Explain plzzz!!!!!!!

  • This topic has 1 reply, 2 voices, and was last updated 11 years ago by MikeLittle.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • October 17, 2013 at 9:24 am #142973
    sweetypie9
    Member
    • Topics: 21
    • Replies: 83
    • ☆☆

    Case: Vitol SA v Norelf Ltd [1996]

    The parties agreed a contract for the sale of a cargo of propane. While the cargo was
    being loaded, the buyers sent a telex to the sellers repudiating the contract on the
    grounds that the loading would not be completed on time. The sellers did not reply
    to the telex. The loading was completed and the vessel sailed with its cargo on
    board.
    The sellers brought a claim (in arbitration) for the difference between the contract
    price for the propane that had been agreed with the buyers and the price at which
    they had been obliged to sell the propane in the market.
    In this case, the arbitration court found that the anticipatory breach of the contract
    by the buyers gave the sellers the right to repudiate the contract. Their decision to
    sell the propane for what they could get in the market was sufficient notification to
    the buyers of their intention to elect to treat the contract as being at an end.

    October 17, 2013 at 1:29 pm #142990
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23311
    • ☆☆☆☆☆

    From the information you have posted I’m not sure that that is anticipatory breach! If the buyer BEFORE the due date for loading had said “I’m cancelling / breaching” that would have been a clear indication of anticipatory breach. If not, it could be argued that the notification was not in anticipation. Rather it was notification AFTER the seller had unconditionally appropriated the goods to the contract ie after the contract start date. However, the Arbitration Court apparently agreed that it was anticipatory

    Your question does not indicate whether the goods were in fact loaded in time according to the time limit imposed by the contract

    Given that it was held to be anticipatory, the seller has the right to sue the breaching buyer for the damage which they have suffered on the deal. In this case above, the seller sold on the market (presumably for the best price the seller could achieve) and sued the buyer for the difference between agreed price in the contract less the value received on the market sale.

    I’m not sure what I else I can say to explain it – it seems to me to be quite straight-forward, but maybe I’m missing something

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT
  • Ark1 on The nature and structure of organisations – ACCA Paper BT
  • zsotuminu on The weighted average cost of capital (WACC) – ACCA Financial Management (FM)
  • Kim Smith on What is Assurance? – ACCA Audit and Assurance (AA)
  • Kim Smith on AA Chapter 17 Questions

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in