- This topic has 3 replies, 2 voices, and was last updated 10 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- You must be logged in to reply to this topic.
OpenTuition recommends the new interactive BPP books for December 2024 exams.
Get your discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › F2 Mock Exam
A company has a budgeted labour cost of $180,000 for the production of 30,000 units per month.
Each unit is budgeted to take 3hours of labour.
The actual cost this month $160,000 for 28,000 units, and 85,000 hours were worked.
What is labour efficiency variance?
Dear Sir,
I have answered 2,000 (adverse) but system showed incorrect 2,000 (Favourable)
efficiency variance = (std hr for act prod ~ Act hrs) std rate
(3 x 28000 ~ 85000) 2
(84000~85000) 2
2000 (Adverse)
The above is my calculation… Please advice
Thank you
You are correct – it is 2,000 adverse
(I will have the exam answer corrected)
Noted with thanks…
You are welcome 🙂