• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Examiner’s report Dec/2011

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Examiner’s report Dec/2011

  • This topic has 1 reply, 2 voices, and was last updated 10 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • June 11, 2014 at 10:09 am #175895
    JOsiely
    Member
    • Topics: 3
    • Replies: 3
    • ☆

    Hello John,
    I learned when you have to work with High low method that has stepped fixed cost, you have to choose the high low activity levels that remain unchanged, to get the variable cost and apply to the activity level after changing.
    So my variable cost would be the same for all the levels if I just calculate (10000-4000)/(3000-1000)= VC. However the answer would be wrong. COuld you please explain me which situations I should apply the high low method with changes in fixed cost in the way explained above, working first with the two points at the “same side” and after appling for the points that I have the change in cost?

    Example 1. The following shows the total overhead costs for given levels of a company’s total output.
    Cost Output
    4,000 1,000
    7,000 2,000
    10,000 3,000
    9,500 4,000
    A step up in fixed costs of $500 occurs at an output level of 3,500 units.
    What would be the variable overhead cost per unit (to the nearest $0.01) using the high low technique?
    Answer examiners 1.67

    Thank you!!!

    June 11, 2014 at 10:35 am #175902
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    If there are several levels of output given, then for high/low you always choose the highest and lowest levels of activity (i.e. output).

    So here, the high is 4,000 units with cost of $9500
    The low is 1,000 units with cost of $4000.

    The difference in the costs of $5,500 is usually due to the extra variable cost of the extra units. However, since 4,000 is above 3,500 it means that $500 of the extra cost is due to the step-up in fixed costs.

    So…..the extra variable cost if 5,500 – 500 = $5,000.

    This is the extra variable cost of an extra 4000 – 1000 = 3000 units.

    So the variable cost per unit is $5,000 / 3,000 = $1.67.

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • hhys on PM Chapter 14 Questions More variance analysis
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • bizuayehuy on Interest rate risk management (1) Part 1 – ACCA (AFM) lectures
  • sokleng on FM Chapter 7 Questions – Investment appraisal – methods
  • Annabelayinloya on IFRS 16 Identifying a lease – ACCA (SBR) lectures

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in