investment $25,000
maintenance
Y1 – $5000
Y2 – $6500
trade-in value
Y1 – $16000
Y2 – $12000
calculation for Y2 maintenance and trade-in why (-$6500+$5500) why not (-$6500+$12000)
is this new calculation?
On ACCA hub is says
Pre S24 Mock Exams – Debrief videos will be available
Tomorrow, 12:00 AM » 11:59 PM
My role is not to answer every question- just for you!!!
This is the answer it gives ……
$ 17495
The EAC is calculated as follows:
Year 0 investment -25000*1 ……………… -25,000
Year 1 maintenance -5000*0.909………………..-4545
Year 2 maintenance and trade-in -6500+5500 = 826
Total PV -30371
Annuity factor for 2 years @10% 1.735
EAC (-30371/1.735) 17,495
There could be a mistake
i agree i think there is a mistake
i know u not only serve me, i just brough out is there any mistake the hub had make. and i did watched the video and they are just explain easy question . i did comment and no one reply. but anyway, thanks for your time
It was just an honest mistake…..they are only humans after all
You must accept sometimes that things aren’t as they seem
And have the ability to move on