Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Decision Making Techniques
- This topic has 1 reply, 2 voices, and was last updated 7 years ago by
John Moffat.
- AuthorPosts
- October 27, 2015 at 7:36 pm #279315
Hi Sir John,
I am just confused on one of the questions I got in revision kit of Kaplan.
It says The Total cost for component is $ 12.5 includes other fixed costs of $2. Direct Labour cost of $4,materials $3, Variable O/H $1, specific fixed cost $2.5.
If the direct labour cost is not used to produce the component, it would be used to increase the production of another item for which there is unlimited demand. The other item has the contribution of $10 pu but requires $8 of labour per unit.
The question asks the maximum price per component, at which buying is preferable to internal manufacture.
When I checked the answer it shows, direct labour of $9. which is calculated as cont. foregone 10/2+direct labour 4.
I didn’t understand from where that 2 came in the contribution foregone.October 28, 2015 at 7:41 am #279356The component needs $4 of labour. The other item required $8 of labour.
So every component we make ‘loses’ us 1/2 of the other item and therefore loses 1/2 of the contribution of the other item.
- AuthorPosts
- You must be logged in to reply to this topic.