• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Damages in building contracts

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA LW Exams › Damages in building contracts

  • This topic has 1 reply, 2 voices, and was last updated 7 years ago by MikeLittle.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • January 29, 2018 at 2:48 pm #433813
    bilo1
    Member
    • Topics: 3
    • Replies: 0
    • ☆

    Q. A entered into a contract with B ltd to construct a wall around the garden of a house she had just purchased. The wall
    was to be 3 metres high to block out a view of rubbish trip.

    B ltd finished the wall on 25 May. However when A came to examine it for te first time she found that it was only
    2.5 metres high and that the rubbish tip was still visible from the top of her garden. The cost of making the wall
    meet the required height is $2000.

    Which of the following remedies would A claim for
    a) Injunction
    b) Nominal damages
    c) Damages of $2000

    There is a Law written in text book that in cases involving building contracts there are two ways in which the damages could, in theory, be 
    measured:

    a)the damages could be the difference in value between the building as it has been completed and its value if it had been properly completed, or

    b) the cost of rebuilding so that it meets the required specifications.

    The usual measure of such damages is the cost of repairing the faulty work known as the ‘cost of cure’. However, this may not be the case where the costs of remedying the defects are disproportionate to the difference in 
    value between what was supplied and what was ordered.

    I could not understand law also. Please explain me the law as well, with the help of any example. Thanks

    January 29, 2018 at 3:04 pm #433816
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23321
    • ☆☆☆☆☆

    This is a past exam question from the days before F4 changed to its current format

    The question is based on the case Ruxley Electronics v Forsyth where a swimming pool was the subject of the contract and the constructors failed to build the pool deep enough

    The cost of draining the water, digging up the tiled floor of the pool, excavating more concrete from the bottom down to the contracted level, re-concreting, re-tiling, re-testing … would have been totally out of proportion when compared with the amenity level reduction of having a swimming pool that wasn’t quite deep enough

    So the court awarded damages and the constructors did not have to rectify the pool dimensions

    However, for a wall to be found to be 50 cm too short … I would have thought that it would not be disproportionate to award the customer the costs of increasing the height … but maybe I’m wrong. What do I know about the technicalities of wall building?

    Maybe the only reasonable solution was to knock the wall down and start again finishing with a 3 meter wall … but I doubt it

    OK?

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘Damages in building contracts’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • o1lim on Discounted Cash Flow Further Aspects, Replacement – ACCA Financial Management (FM)
  • julio99 on Impairments – Impairment (CGU) – ACCA Financial Reporting (FR)
  • effy.sithole@gmail.com on EPS – diluted EPS Example – ACCA Financial Reporting (FR)
  • Ken Garrett on The Finance Function in the Digital Age – CIMA E1
  • DeborahProspect on ACCA SBR Specimen Exam 2 Question 1

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in