CostingForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › CostingThis topic has 3 replies, 2 voices, and was last updated 2 years ago by John Moffat.Viewing 4 posts - 1 through 4 (of 4 total)AuthorPosts September 18, 2022 at 8:35 pm #666697 teshwarParticipantTopics: 45Replies: 30☆☆House Co also plans to manufacture 90 sofas in June.Materials 10m of fabric @$50 per meter =$500How many metres of fabric should be purchased if 10% of material is wasted during production process?Answer90 * 10m = 900m Plus waste 100m Purchase 1000mSir John, I don’t understand how they got the 100m September 19, 2022 at 7:40 am #666706 John MoffatKeymasterTopics: 57Replies: 54628☆☆☆☆☆For every 100 metres of fabric the buy, the 10% (i.e. 10 metres) will be wasted and only 90 meters will be available for production.Putting it the other way round, for every 90 needed for production they will need to buy 100. September 19, 2022 at 5:38 pm #666729 teshwarParticipantTopics: 45Replies: 30☆☆Thank you September 19, 2022 at 6:47 pm #666738 John MoffatKeymasterTopics: 57Replies: 54628☆☆☆☆☆You are welcome 🙂AuthorPostsViewing 4 posts - 1 through 4 (of 4 total)The topic ‘Costing’ is closed to new replies.