Cost plus method Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA APM Exams › Cost plus method This topic has 1 reply, 2 voices, and was last updated 6 years ago by Ken Garrett. Viewing 2 posts - 1 through 2 (of 2 total) Author Posts September 2, 2019 at 8:33 pm #544246 zkaayParticipant Topics: 212Replies: 98☆☆☆ Hi sir, When in scenario it says using Cost plus method Does it mean total cost plus or variable cost plus? Thanka September 3, 2019 at 6:01 pm #544566 Ken GarrettKeymaster Topics: 10Replies: 10652☆☆☆☆☆ It should usually mean full cost (ie, total absorption cost) plus. Author Posts Viewing 2 posts - 1 through 2 (of 2 total) You must be logged in to reply to this topic. Log In Username: Password: Keep me signed in Log In