- This topic has 3 replies, 2 voices, and was last updated 10 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- You must be logged in to reply to this topic.
Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Cost absorption
Hi I met a question for cost absorption
A company uses absorption costing with a predetermined hourly overhaed absorption rate. The following situations have both occured:
(i) Actual overhaed expenditure exceeded planner expenditure; and
(ii) Actual hours worked were less than the planned hours
Which of the statement is correct
A Situation (i) would cause overhaeds to be over absorbed and situation (ii) would cause overhaeds to be under absorbed
B Situation (i) would cause overhaeds to be under absorbed and situation (ii) would cause overhaeds to be over absorbed
C Both situations would cause overheads to be over adsorbed
D Both situations would cause overheads to be under adsorbed
Please explain to me for this question. Thank you
The pre-determined absorption rate will have been based on the budgeted/planned expenditure and the budgeted/planned hours.
The total absorbed is the actual hours x the absorption rate.
So if the actual expenditure is more than planned, the overheads will have been under-absorbed.
If the actual hours are less than the planned hours, then the overheads will have been under-absorbed.
I do suggest that you watch the free lectures on absorption costing.
thank you
You are welcome 🙂
(and are you watching the lectures?)
