June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Cost

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Cost

  • This topic has 1 reply, 2 voices, and was last updated 8 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • February 16, 2017 at 11:03 am #372691
    anu1234
    Member
    • Topics: 78
    • Replies: 65
    • ☆☆

    Time for first batch of 50 units is 400 hours but labor budget is the subject of learning rate and it is 90%. Rate of pay for labour is $12 per hour. Business had received and satisfied an order of 600 units but it has nle received a second order for another 800 units. value of b is -0.152 . What is the cost of second order ?

    Time for first order is 400*50raised to 0.-152 =220.7 hours.

    I dont understand what to do then . Please help

    February 16, 2017 at 3:46 pm #372733
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54680
    • ☆☆☆☆☆

    You must have an answer in the same book in which you found the question, and so you should ask about whatever part of the answer you do not understand! (If you do not have an answer then you are wasting your time – you should be using a Revision Kit from one of the ACCA approved publishers.)

    The time for the first order is not what you have written at all!

    The first order was for 600 units which is 600/50 = 12 batches.
    Therefore the average time per batch is 400 x 12^(-0.152), and the total time is 12 times the average time.

    The second order is for another 800/50 = 16 batches, which bring the total up to 28 batches.

    So you need to calculate the total time for 28 batches and then subtract the total time for 12 batches.

    Have you actually watched my free lectures on learning curves?

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘Cost’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • manahylilyas on The financial management environment – ACCA Financial Management (FM)
  • poojam on Objective of financial reporting – ACCA Financial Reporting (FR)
  • mm3677 on IAS 16 Accounting for a revaluation – CIMA F1 Financial Reporting
  • Anastesia123 on MA Chapter 1 Questions Accounting for Management
  • John Moffat on MA Chapter 26 Questions Variance Analysis

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in