• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Contract price

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FM Exams › Contract price

  • This topic has 4 replies, 2 voices, and was last updated 1 year ago by LMR1006.
Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • August 30, 2023 at 11:27 am #690959
    alawi sayed
    Participant
    • Topics: 301
    • Replies: 352
    • ☆☆☆☆

    Hello Sir,

    Q 86 on Kaplan 2022-2023 Exam kit

    A  company  is  considering  investing  in  a  two?year  project.  Machine  set?up  costs  will  be $125,000,  payable  immediately.  Working  capital  of  $4,000  is  required  at  the  beginning  of the contract and will be released at the end. 
    Given  a  cost  of  capital  of  10%,  what  is  the  minimum  acceptable  contract  price  (to  the nearest thousand dollar) to be received at the end of the contract? 
    $   

    In the above question it is asking the minimum contract price

    The cash flows was discounted and the NPV was divided by the discount factor to give the minimum price of the contract.

    I am not able to understand the logic behand this calculation

    can you please clarify the amount of $152,000 as minimum contract price

    Why we divide the NPV again to get the contract price ,

    Thanks,

    Answer

    $152,000 
    PV of contract price should just cover the PV of the project costs to be acceptable. 
    Time  Flow  Discount @ 10% pv

     
     0 (125000) 1 (125000)
    1 (4000) 1 (4000)
    2 4000 0.826 3304
    ———
    -125696
        ________
       
    Therefore, contract price @ time 2 × 0.826 = 125,696 
    Price = 125,696/0.826 = $152,174 or $152,000 to the nearest $000. 

    August 30, 2023 at 8:33 pm #690997
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1478
    • ☆☆☆☆☆

    You are calculating the PV of the contract

    The minimum acceptable contract price is determined by calculating the net present value (NPV) of the project’s cash flows.

    The NPV represents the present value of the project’s inflows and outflows, discounted at the cost of capital rate. In this case, the machine set-up costs of $125,000 and the working capital of $4,000 are considered outflows at time 0.
    The working capital is released at the end of the contract, resulting in a cash inflow time 2.

    PV (1To calculate the minimum acceptable contract price, the NPV is divided by the discount factor. The discount factor is calculated using the cost of capital rate and the time period of the project. In this case, the project is a two-year project, so the discount factor is calculated as 1 / (1 + 0.10)^2 = 0.826

    (125)+(4)+ [ 4* 0. 826] = (125.96)
    This is the contract at time 2

    But we need a PV of it so we take the (125.96) / 0.826 = 152.174 or 152k

    September 7, 2023 at 12:10 pm #691634
    alawi sayed
    Participant
    • Topics: 301
    • Replies: 352
    • ☆☆☆☆

    Hi Tutor,

    My confusion is if we calculate the NPV of the contract

    (125)+(4)+(4* 0.826) = (125.96)
    This is the contract at time 2

    you said it is the contract at time two ,but here we have the present value the cash flow of year two is already discounted to year 0

    So shouldn’t it be the contract value at 0 because we already discounted to time 0
    when we multiply 4* .826

    Can you please clarify more.

    Thanks,

    September 7, 2023 at 7:00 pm #691662
    alawi sayed
    Participant
    • Topics: 301
    • Replies: 352
    • ☆☆☆☆

    Hi Tutor,

    Can I get the reply,

    Thanks,

    September 7, 2023 at 7:13 pm #691664
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1478
    • ☆☆☆☆☆

    It’s what is the minimum acceptable contract price (to the nearest thousand dollar) to be received at the end of the contract?

    So PV of an end of the contract

    (125)+(4)+ [ 4* 0. 826] = (125.96) NPV of projects cash flows

    But we need value today so we take the (125.96) / 0.826 = 152.174 or 152k
    PV – calculate the minimum acceptable contract price, the NPV is divided by the discount factor

  • Author
    Posts
Viewing 5 posts - 1 through 5 (of 5 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ojoggo on The Statement of Financial Position and Income Statement (part a) – ACCA Financial Accounting (FA) lectures
  • hhys on PM Chapter 4 Questions Environmental Management Accounting
  • singhjyoti on Conceptual Framework – ACCA SBR lecture
  • John Moffat on Time Series Analysis – ACCA Management Accounting (MA)
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in