Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › Construction contracts :what to do with the specialised equipment
- This topic has 5 replies, 3 voices, and was last updated 10 years ago by  MikeLittle. MikeLittle.
- AuthorPosts
- June 2, 2015 at 6:54 pm #252101Hi mike I have seen a few different treatments and maybe I am not putting it together correctly. In the MCQ revision mock exam there is a question, ” Anges entered.. Contract price 20m…costs 4m..plus est to compl 12m..in addition an item of plant for exclusive use on the contract for $1m.uel =2years (so depreciation is 125, 3 months to year end.) 
 Invoiced and recd was 7m…the stage of completion basis is progress billing as proportion of contract price.( I took that as 7/20=35%)My version: 
 Income statement
 Rev 35%x20m = 7m
 Costs 35%x (4+12+1)=5.95m
 Attrib profit 1.05m
 -depreciation 0.125
 =925Contract liab 
 Costs 4+0.125=4.125m
 +Attrib profit. 925
 -Invoiced 7
 =-1.95..This gave none of the answers!… So I took out the plant.. Rev 35%x20=7 
 Costs 35%x(4+12)=5.6
 Attrib prof =1.4
 -depr 0.125
 =1.275Costs 4+.125=4.125 
 +Attrib pr =1.275
 =5.4
 -inv 7
 =-1.6Which gave me the right answer according to the MCQ tests , is this working correct do you think ? Cheers Hugh June 2, 2015 at 7:19 pm #252128I just did the MCQ Test and this question too. June 2, 2015 at 7:27 pm #252132I used Kaplan to get the working format. First I got the total profit for the whole project: Revenue:20M 
 Less:Total Costs: (16M)
 Profit: 4MThen I got the attributable profit for the period: As per the question the stage of completion basis is progress billing as proportion of contract price.( I took that as 7/20=35%). This is correct. 35% of 4M=1.4M So from here I proceeded to prepare the income statement: Sales(Bal. figure):5.4M 
 Costs for the period:(4M)
 Profit for the period: 1.4M(as above)Then to get the SFP figures: Costs incurred to date: 4M 
 Profit for the period: 1.4
 Progress payment: (7M)
 Due to Customer: (1.6)-LiabilityJune 2, 2015 at 7:58 pm #252144Why would you not take 35% of 20 for the revenue figure, 35% of total costs and that would give you 35% of the profit? Revenue. 7.0 
 Costs. 5.6
 Profit. 1.4Eller, please restrict your input to the general forum Thanks June 3, 2015 at 9:33 am #252340Why wouldn’t you take*35%* of 17=5.95m? June 3, 2015 at 10:18 am #252352Where does 17 fit into it? 
- AuthorPosts
- You must be logged in to reply to this topic.



