Dear Tutor, First, let me say thank you for answering all our questions, very much appreciated.
And another question, of course 🙂 If have enough information in the question to calculate the percentage of completion using both ways (work certified/total contract price and costs incurred to date/total estimated costs), and the resultant percentages are different, which one should I use?
I can’t see that he will do that to you. He would more likely give you the percentage complete OR he’ll state within the question which method the company has adopted.
Thank you for all your nice comments and a happy asparagus day to you