• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Construction contract Profits

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › Construction contract Profits

  • This topic has 8 replies, 2 voices, and was last updated 7 years ago by MikeLittle.
Viewing 9 posts - 1 through 9 (of 9 total)
  • Author
    Posts
  • April 26, 2018 at 7:09 pm #449010
    iyamu
    Participant
    • Topics: 286
    • Replies: 171
    • ☆☆☆

    Sir I was able to do example 4 but I am totally stock at example 5.

    I could not even figure at the solutions from the back of the text as there was no explanation to arriving at those solution figures provided.

    Could you pls, I assume you have the questions with you but if not I can write them out here.

    Thanks in anticipation.

    April 26, 2018 at 8:06 pm #449013
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23333
    • ☆☆☆☆☆

    I believe that this is the question where, at the end of year 2, a loss of $140,000 is forecast

    That anticipated loss should be recognised in full and, to do that, the cumulative costs figure needs to be extraordinarily high at $790,000

    Are you ok from there?

    April 26, 2018 at 10:29 pm #449018
    iyamu
    Participant
    • Topics: 286
    • Replies: 171
    • ☆☆☆

    yr1 yr 2 yr3
    contr value 1m 1m 1.2m

    cost to date, gen 300,000 500,000 800,000
    spec to date 40,000 40,000 190,000
    Est to complete 500,000 600,000 –
    Amt invoiced 390,000 610,000 1,150,000
    amt rec 400,000 630,000 1,100,000
    % complete 30% 65% 100%

    The additional $200,000 contract value arose in year 3 from agreed variation with the the as a result of customer’s delays involving additional costs for the constructor of $150,000, none of which was foreseen at the end of year.
    prepare relevant extracts from the statement of Comp Income SOFP for each of the 3 years.

    Wk1 SOPL
    yr1 yr2 yr3
    Rev reco 65% of 1m 300,000 350,000 (650-300) 1,200,000

    costs rec period 40,000
    gen3 0%(300+500)=240,000 (280,000) stock stock

    est profit 20,000 ^^ ^^

    April 27, 2018 at 6:22 am #449039
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23333
    • ☆☆☆☆☆

    I’m not sure what you want from me here – there doesn’t appear to be a question aimed at me!

    April 27, 2018 at 4:47 pm #449119
    iyamu
    Participant
    • Topics: 286
    • Replies: 171
    • ☆☆☆

    Well I just copied all the questions out so you can see. Example 5 of construction contract profits.

    For the 1 year , second year and third year I was able to calculate the revenue recognized .

    For the 1 year I calculated 20,000 as estimated profit recognized but I can not calculate further for the 2 year and third year. Pls assist .

    April 27, 2018 at 6:49 pm #449131
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23333
    • ☆☆☆☆☆

    Year 2:

    general costs to date 500,000
    period specific costs to date 40,000
    estimated costs to complete 600,000

    therefore total costs on the contract are estimated to be 1,140,000

    contract revenue is only 1,000,000

    so forecast loss is 140,000

    Now can you sort it out?

    April 27, 2018 at 7:37 pm #449135
    iyamu
    Participant
    • Topics: 286
    • Replies: 171
    • ☆☆☆

    Yes I got the forecast cost be 140,000. But I did not know what to do because I saw 280,000 , 510,000 and 200,000 as cost recognized for the years respectively. For the 280,000 , that I know but others I don’t know.

    From the question there is 150,000 additional costs which was not foreseen at the end of yr 2.

    Pls help me sir.

    April 27, 2018 at 11:11 pm #449138
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23333
    • ☆☆☆☆☆

    So that $150,000 is period specific for year 3

    “I saw 280,000 , 510,000 and 200,000 as cost recognized for the years respectively”

    $280,000 is calculated as 30% of total anticipated costs on the contract

    Year 2 a loss is forecast so, if we’re recognising 65% of revenue (cumulatively) ie $650,000 accumulated revenue as at the end of year 2, and we need to recognise a forecast loss of $140,000, then cumulative costs to be recognised must be $790,000

    But we have already recognised $280,000 costs in year 1 so there’s only a further $510,000 to recognise in year 2

    Better?

    April 30, 2018 at 8:08 am #449432
    MikeLittle
    Keymaster
    • Topics: 27
    • Replies: 23333
    • ☆☆☆☆☆

    > 2 days and no response so I’m closing the thread

  • Author
    Posts
Viewing 9 posts - 1 through 9 (of 9 total)
  • The topic ‘Construction contract Profits’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • omostofi86 on Conceptual Framework – ACCA SBR lecture
  • Anonymously on Chapter 4 – Tax Adjusted Trading Profit – Individuals TX-UK FA2023
  • John Moffat on Cost Classification and Behaviour part 1 – ACCA Management Accounting (MA)/you
  • xtal2000 on Chapter 13 Capital Gains Tax – Individuals – Reliefs TX-UK FA2023
  • bhumichaudhary on Cost Classification and Behaviour part 1 – ACCA Management Accounting (MA)/you

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in