Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › construction contract help please…
- This topic has 4 replies, 3 voices, and was last updated 14 years ago by MikeLittle.
- AuthorPosts
- May 30, 2010 at 7:10 pm #44282AnonymousInactive
- Topics: 16
- Replies: 32
- ☆
The contractor is in the intermediate stage of completion of a construction contract for the building of a new privately owned road bridge over a river estuary.
Approx duration of contract 3 years
Date of commencement 1 October 1998
Total contract price $40 million
Estimated total cost $28 million
An independent surveyor certified the value of the work in progress as follows:
on 31st March 1999 $12 million
on 31st March 2000 $ 30 million (including the $12m in 1999)
Total costs incurred at:
31 March 1999 $ 9m
31 March 2000 $28.5m (including $9m in 1999)
Progress billings at 31 March 2000 were $25m
On 1 April 1999 the contractor agreed to a contract variation that would involve an additional fee of $5m with associated additional estimated costs of $2mThe costs incurred during the year to 31 March 2000 include $2.5m relating to replacement of some bolts which had been made from material that had been incorrectly specified by the firm of civil engineers who were contracted by the the contractor to design the bridge. These costs were not included in the oiginal estimates but the contractor is hopeful that he can recover this amount from the firm of civil engineers. Advice to the contractor from lawyers is that there is a 60% chance of success.
Percentage of completion of the contract is based on value of the work certified to date compared to the total contract price.I’m sorry for a such a long question. I wanted to know why is $2.5m rectification costs included in ”costs incurred to date” shouldn’t it be excluded? Also how should we treat the extra $2m costs???
May 30, 2010 at 11:11 pm #61696AnonymousInactive- Topics: 0
- Replies: 26
- ☆
Rectification costs are charged as a period cost in which they occur.the extra 2m will be added to the already total estimated costs of 28m.this gives a total estimated cost of 30m.this should be multiplied with the % of completion which in 20X0 will be 30/45…which is value of work certified/total contract price..
this gives you a total cost of 30*30/45=20m..
20m-cost incurred in 19W9 which is 8.4…
20-8.4=11.6
+
2.5 rectification cost which should be charged completely in 20X0=14.1
hope this helps u..June 3, 2010 at 2:30 pm #61697thanks cuid
June 3, 2010 at 6:13 pm #61698AnonymousInactive- Topics: 16
- Replies: 32
- ☆
thanks cuid got it
June 4, 2010 at 3:46 pm #61699good
- AuthorPosts
- You must be logged in to reply to this topic.