Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA FR Exams › con struction contract
- This topic has 5 replies, 2 voices, and was last updated 9 years ago by MikeLittle.
- AuthorPosts
- May 22, 2015 at 7:37 am #247849
Sir,
how to calculate estimated profit and further what to doTentacle is involved in the construction of a residential apartment building. It is being accounted for using
the percentage of completion basis in IAS 11 Construction contracts. The recognised profit at 31 March
20X7 was $1·2 million based on costs to date of $3 million as a percentage of the total estimated costs of $6
million. Early in May 20X7 Tentacle was informed that due to very recent industry shortages, building
materials will cost $1·5 million more than the estimate of total cost used in the calculation of the percentage
of completion. Tentacle cannot pass on any additional costs to the customer
how to calculateState and quantify how items above should be treated when finalising the financial statements of Tentacle
for the year ended 31 March 20X7IAS 11 requires that the profit on the contract be recalculated to take into account these additional costs.
Profit is based on costs to date as a percentage of total costs. As costs to date are $3m and total costs $6m,
the percentage is currently 50%. This will change when the additional costs are included as follows:
Costs to date Total expected
costs
% Total expected
profit
Profit to date
$m $m $m $m
Original 3 6 50% 2.4 1.20
Additional costs – 1.5 (1.5) –
Amended 3 7.5 40% 0.9 0.36
Recognised profit for the year to 31 March 20X7 should therefore be restated as $360,000. $840,000 (1.2m
– 0.36m) will be written off in the income statement and adjusted in the statement of financial position
against amounts due to/from customers.May 22, 2015 at 7:52 am #247864You appear to have answered the question – which bit of it do you need me to expand upon?
May 22, 2015 at 8:01 am #247868sir how to calculate estimated profit 2.4 and profit to date 0.36
May 22, 2015 at 8:06 am #247872The stage reached is based on the percentage of costs incurred as a proposition of the total estimated costs
Before we learned the bad news of the building materials cost increases, cost to date was $3 million, ie 50% of the total estimated costs. And, in the process of recognising 50% of the costs, a profit figure of $1.2 million was also recognised
Well, if $1.2 million is the profit on half the contract, what is the profit on 100% of the contract?
May 22, 2015 at 8:15 am #247879thank you so much i got it
May 22, 2015 at 8:20 am #247881That’s good. You’re welcome
- AuthorPosts
- You must be logged in to reply to this topic.