• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

Cofold construction company september 2018 1b

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA SBL Exams › Cofold construction company september 2018 1b

  • This topic has 3 replies, 2 voices, and was last updated 4 years ago by Ken Garrett.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • January 24, 2021 at 9:41 am #607731
    rimshy
    Member
    • Topics: 95
    • Replies: 91
    • ☆☆

    I cannot understand when its talking about
    criteria stated by transport minister to reduce environmental impact what does it mean by introduction of road ecology measures such as wildlife crossings which can minimise impact on local species

    Cost constraint: its given transport minister has stated low prce criteria..what could be its impact like how does it reduce our profit margins below 8% if the costs over runs ….please explain this point also

    January 24, 2021 at 10:08 am #607732
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10590
    • ☆☆☆☆☆

    Vehicles travel on roads. Vehicles sometimes collide with animals and kill or injure them. Some countries/regions where there are important animal migrations construct underpasses for the animals.

    If CC wants to achieve 8% and it has been selected on the basis of a low price if costs increase then either the 8% will not be achieved (assuming the selling price can’t be increased) or the company might be tempted to try to save costs by producing poorer quality work.

    January 26, 2021 at 8:45 am #608042
    rimshy
    Member
    • Topics: 95
    • Replies: 91
    • ☆☆

    Please explain how local communities and government are major stakeholders that should be included in project initiation document and how construction of road affects local communities and government

    January 26, 2021 at 9:48 am #608065
    Ken Garrett
    Keymaster
    • Topics: 10
    • Replies: 10590
    • ☆☆☆☆☆

    Communities: disruption as work carried out, additional traffic perhaps, additional noise and pollution, additional convenience and perhaps additional safety

    Government: pays for it. May affect government popularity and election prospects etc.

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘Cofold construction company september 2018 1b’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • mrjonbain on What is Assurance? – ACCA Audit and Assurance (AA)
  • Ejueyitsi-Toju on What is Assurance? – ACCA Audit and Assurance (AA)
  • sadik.sadka on How to make the best use of OpenTuition
  • SONIC916 on Lessee accounting – ACCA (SBR) lectures
  • AkinMike on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in