• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exam Results

Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

Choice of Contract

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Choice of Contract

  • This topic has 3 replies, 2 voices, and was last updated 2 years ago by LMR1006.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • April 20, 2023 at 7:30 pm #683275
    VikasK
    Participant
    • Topics: 98
    • Replies: 118
    • ☆☆☆

    Hello Sir hope you are doing well.
    I have a question regarding “Choice of Contract” question which is in the kit of Kaplan.

    The following is the extract of the question

    “A company in the civil engineering industry with headquarters located 22 miles from London undertakes contracts anywhere in the United Kingdom.

    The company has had its tender for a job in north-east England accepted at $288,000 and work is due to begin in March 20X3. However, the company has also been asked to undertake a contract on the south coast of England. The price offered for this contract is $352,000.

    Both of the contracts cannot be taken simultaneously because of constraints on staff site management personnel and on plant available. An escape clause enables the company to withdraw from the contract in the north-east, provided notice is given before the end of November and an agreed penalty of $28,000 is paid.

    Req As the management accountant to the company present comparative statements to show the net benefit to the company of undertaking the more advantageous of the two contract

    There is a specific point, in the question which states. “The plant which would be needed for the south coast contract has been owned for some years and $12,800 is the year’s depreciation on a straight-line basis. If the north-
    east contract is undertaken, less plant will be required but the surplus plant will be hired out for the period of the contract at a rental of $6,000”.

    Sir the suggested answer has taken $6000 as a relevant (opportunity cost) in case the contract on South Coast is accepted. Which i totally understand.

    However, shouldn’t this $6000 also be an incremental benefit/revenue for contact at North East England under the comparative statement .

    As in case North East Contract is undertaken, less plant would be needed a s surplus plant will be hired out for the period.

    April 21, 2023 at 1:53 pm #683310
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1520
    • ☆☆☆☆☆

    You are happy that $28,000 is the penalty payable if you go for South-coast and withdraw from North-east. And the same thing applies to the North-east contract if you don’t undertake it so the $6,000 is an opportunity cost it could be hired out. Agreed

    The question states that both contracts cannot be undertaken simultaneously because of the constraints on staff site personnel and on plant availability. It is one of the other!

    So you can’t look at it from any other perspective than as an opportunity cost of $6000 South-coast or income for North-east. Not both.

    In this case if income for North-east

    NE 288,000 – 199,600 + 6000 = 94,400
    SE 352,000 – 264,400 = 87,600
    Diff is still 6,800

    April 22, 2023 at 3:14 pm #683357
    VikasK
    Participant
    • Topics: 98
    • Replies: 118
    • ☆☆☆

    Thankyou for your response Tutor. But i think there are some typing error in your answer which is making it difficult for me the understand your explanation.

    My Approach to this question was that i looked at each of the contract at a time along with their relevant cash flow.

    That i first saw the relevant cash flow from the North East Contract and then i saw the relevant cash flow from South Coast Contract. Because of which this problem arised.

    Can you please tell me the approach to use because of which this problem does not arise. Thankyou in Advance:)

    April 22, 2023 at 4:50 pm #683362
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1520
    • ☆☆☆☆☆

    The question states that both contracts cannot be undertaken simultaneously because of the constraints on staff site personnel and on plant availability.

    Therefore an opportunity cost for $6000 South-coast which you agreed with

    or you could look at this as income to the North-east.

    In this case if there is income for North-east

    NE 288,000 – 199,600 + 6000 = 94,400

    SE 352,000 – 264,400 = 87,600

    Diff is still 6,800

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • @zeba.aida on How to make the best use of OpenTuition
  • Myo94 on ACCA BT Chapter 20 – Marketing – Questions
  • siu18 on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • aashikahamed on CIMA P2 Chapter 1 Test
  • John Moffat on PM Chapter 9 Questions Short-term decision making

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in