If in a question we are asked to find Project specific discount factor and are given asset beta we don’t need to degear it right? as there is no financial risk so we can straight move on with regearing the asset beta and then applying the CAPM formula to find the rate
That is correct 🙂
Thankyou 🙂
You are welcome 🙂