- April 28, 2013 at 8:07 pm #123800
Hi,
I am doing a mock paper as part of the bpp course, and there is a question asking to prepare a budget that will be useful for management control purposes, could you please tell me how I should approach this question. The question has given fixed budgeted results and actual results and information about staff turnover.
Thanks
April 28, 2013 at 8:37 pm #123808<cite> @maes said:</cite>
Hi,I am doing a mock paper as part of the bpp course, and there is a question asking to prepare a budget that will be useful for management control purposes, could you please tell me how I should approach this question. The question has given fixed budgeted results and actual results and information about staff turnover.
Thanks
April 29, 2013 at 10:28 am #123854I would think that they are wanting you to prepare a flexed budget – rewriting the original fixed budget for the actual levels of sales and production.
April 29, 2013 at 10:49 am #123868Thanks John, so I will take the cost per unit from the original fixed budget and times that by the actual number of units that were produced?
Thanks
April 29, 2013 at 1:15 pm #123944Yes – that’s correct 🙂