Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Budget
- This topic has 3 replies, 2 voices, and was last updated 5 years ago by John Moffat.
- AuthorPosts
- December 30, 2018 at 8:53 am #499473
Sir, I am a bit confused with the term budgetary system and budgeting process.
are there actually the same meaning?
as I read the BPP textbook I found out that sometime they mention budgetary system, while sometime they mention budgeting process.What are the type of budgeting process?
Although I know it would not come out in ACCA exam, I hope to have an understanding on it.
Thanks
December 30, 2018 at 10:26 am #499485Strictly, the budgetary system is the type of budget that is being prepared (e.g. a rolling budget, or incremental budget, or zero based budget – I explain what these are in my free lectures).
The budgeting process is how the preparation is organised e.g. who is responsible for which part of it, who is coordinating it all and approving it all.Do watch my free lectures on budgeting. The lectures are a complete free course for Paper PM and cover everything needed to be able to pass the exam well.
December 30, 2018 at 11:14 am #499489Is that means the planning and control cycle is considered as the budgeting process? (as to page 220 BPP Textbook 2016/2017)
(first we need identify objectives, followed by identify potential strategies, evaluate strategies, identify possible course of action)In summary,
Budgeting system is we use what method to prepared the budget.
Budgeting process is how we are going to apply the method of budgeting (zero-based, incremental) into practical.
The above is what I understand from sir your explaination above.
Is it correct?December 30, 2018 at 5:27 pm #499502Ok have no idea what the BPP Study Text says – if you are watching my free lectures then you do not really need the Study Text (just, obviously; the Revision Kit).
Otherwise, what you write is correct 🙂