As per answer to this question, the probability of total unit cost exceeding $41.21 is 32%. Anyone please explain, how did they get that 32%. Many thanks
Hi Daisy
you count the figures that > 41.21 in table 1 and then sum the probability corresponding in table 2 you will get 32%
peace
Thank you so much peace, you really made it clear. Thanks again.