this question requires us to determine optimal production plan and maximise profit by using linear programming graph.
It seems to me that they made a mistake when calculate points and drew a line for material’s constraint.
Constraint for material is: 0,5x+0,75y=12000 In my opinion for x=0, y=16000 and for y=0 x=24000. So we have 2 points (x=0,y=16000) and (x=24000, y=0)
Whereas in BPP practice and revision kit they have 2 points (x=0,y=24000) and (x=16000, y=0)
Has anyone noticed that?